Duke Energy implodes smokestacks at retired H.F. Lee coal-fired power plant



December 20, 2013

Duke Energy Progress' demolition specialist this morning imploded the smokestacks at the retired H.F. Lee Steam Plant as part of the company's ongoing effort to transition to cleaner energy sources.

This was the first of two implosion events that will occur at the site. The second will demolish the boilers and is scheduled for the spring of 2014.

Duke Energy's ultimate goal for retired coal-fired sites such as H.F. Lee is to dismantle the equipment and buildings, and restore the site to ground level. After the second implosion event, Duke Energy will be able to complete demolition activity and begin restoring the land.

Restoration involves filling, grading and seeding the land. The company plans to complete this phase by late-2014 and will continue to own and steward the land in the future.

The coal plant served the region for more than 60 years and today's event marks a milestone in the history of the site.

Duke Energy replaced the coal plant with a new 920-megawatt (MW) natural gas-fired combined cycle plant that began serving customers in December 2012.

Duke Energy's investment in five new plants, including the one located at the H.F. Lee Energy Complex, totals $9 billion. The new, state-of-the-art technology allows the company to retire approximately 3,400 MW of older coal units by the end of 2013. That number will grow to nearly 6,300 MW over the next few years.

These retired plants will enter the decommissioning and demolition program and move through a process similar to H.F. Lee's.

Video footage of the implosion event is available by clicking here.

Pictures of the implosion event and energy complex are available by clicking here.

Customers interested in learning more about the decommissioning project can visit www.duke-energy.com/coal-decommissioning.

About Duke Energy Progress

Duke Energy Progress, a subsidiary of Duke Energy (NYSE: DUK), provides electricity and related services to nearly 1.5 million customers in North Carolina and South Carolina. The company is headquartered in Raleigh, N.C., and serves a territory encompassing more than 34,000 square miles including the cities of Raleigh, Wilmington and Asheville in North Carolina and Florence and Sumter in South Carolina. More information is available at www.progress-energy.com.

Headquartered in Charlotte, N.C., Duke Energy is a Fortune 250 company traded on the New York Stock Exchange under the symbol DUK.

For more information :

Organization:
Duke Energy
Address:
526 S Church St
Charlotte, North Carolina
United States, 28202-1904
www.duke-energy.com


Link http://www.electricenergyonline.com/detail_news.php?ID=464939
BACK SEND PRINT
Most consulted news
White Papers

Contact us

Jaguar Expo Inc
1160 rue Levis, Suite 100
Terrebonne (Quebec) J6W 5S6

Tel.: 450-471-0796
Toll free: 888-332-3749
Fax: 450-471-5443 . 888-243-4562

info@electricenergyonline.com
www.electricenergyonline.com

  Press

  Jobs

  Events

  Subscription

  News

  Magazine

  News on your smartphone

© 2014, Jaguar Media inc. All rights reserved. 1996-2014