Siemens and KOSPO complete the Andong power plant in South Korea in record time



April 7, 2014

The Andong combined cycle power plant (CCPP) in South Korea was erected in a record time of only 24 months. This liquefied natural gas (LNG) fired plant has an electrical capacity of 417 megawatts (MW), making it the second Siemens operating H-class-based combined-cycle power plant in Asia with an efficiency level of more than 60 percent. The owner and operator is Korea Southern Power Co. Ltd. (KOSPO), a leading power supply utility. KOSPO teamed up with Siemens and GS E&C in successfully accomplishing this record schedule based upon their common experience in power construction industry. Designed for 250 starts per year, with a startup time of only 30 minutes from standstill to full load, the Andong CCPP is particularly flexible, allowing it to react optimally to the rapidly changing challenges posed by the Korean power market.

The Andong CCPP is located in the city of the same name in the province of Gyeongsangbuk-do. The plant is designed as a single-shaft power plant. As the consortium leader with its partner GS E&C, Siemens was not only responsible for the turn-key erection of the plant, but also supplied the major components - one SGT6-8000H gas turbine, one SST6-5000 steam turbine, one SGen6-2000H generator and a Benson heat recovery steam generator. The SPPA-T3000 I&C system and other auxiliary systems are also part of the package. Furthermore, Siemens has signed a maintenance contract with a term of ten years for the main components.

"The trustful relationship developed with KOSPO and our partner GS E&C made it possible to execute this high efficient H-class single shaft power plant in a record time with highest quality to support the high power demand in the Andong area. The project execution also was a benchmark in terms of health and safety and zero harm in Korea,' said Lothar Balling, Executive Vice President and head of global project management in the Siemens Energy Power Generation Division.

"We place special emphasis on maximized efficiency, operational flexibility and environmental friendliness. For that reason we opted for a solution provided by Siemens, which features cutting-edge power plant technology. The plant's quality and the fast project execution once again proved that Siemens is a very experienced and reliable partner for us," declared Lee SangHo, President & CEO of Korea Southern Power Co. Ltd.

Siemens also has three additional combined-cycle plants with H-class gas turbines under construction in South Korea with a total capacity of 2,500 MW which are scheduled to commence operation over the course of 2014 and 2015.

In October 2013, Siemens incorporated a new company, Siemens Energy Solutions Ltd. in Seoul/South Korea, which will act as its new Regional Headquarters to serve the Asian and Middle Eastern power plant solutions market out of the region. The company is expected to grow its staff to more than 500 employees in 2017.

Highly efficient combined-cycle power plants and the associated service are part of Siemens' Environmental Portfolio. Around 43 percent of its total revenue stems from green products and solutions. That makes Siemens one of the world's leading providers of eco-friendly technology.

The Andong plant in South Korea is Siemens's second combined cycle power plant in Asia with an efficiency of more than 60 percent. Siemens was together with its partner responsible for the turnkey construction and delivered an SGT6-8000H gas turbine, an SST6-5000 steam turbine, an SGen6-2000H generator as well as a Benson heat recovery steam generator.

This press release and a press picture can be found at http://www.siemens.com/press/pi/EP201404035e

For further information on the SGT6-8000H gas turbine, please see www.siemens.com/energy/SGT6-8000H

The Siemens Energy Sector is the world's leading supplier of a broad spectrum of products, services and solutions for power generation in thermal power plants and using renewables, power transmission in grids and for the extraction, processing and transport of oil and gas. In fiscal 2013 (ended September 30), the Energy Sector had revenues of EUR26.6 billion and received new orders totaling approximately EUR28.8 billion and posted a profit of approximately EUR2 billion. On September 30, 2013, the Energy Sector had a work force of approximately 83,500. Further information is available at: www.siemens.com/energy.

For more information :

Organization:
Siemens
Address:
Freyeslebenstrasse 1
Erlangen, Germany
Germany, 91058
www.energy.siemens.com

Contact person:

Gerda Gottschick
Media Contact
Tel: +49 9131 18-85753
E-mail: gerda.gottschick@siemens.com


Link http://www.electricenergyonline.com/detail_news.php?ID=477192
BACK SEND PRINT
Most consulted news
White Papers

Contact us

Jaguar Expo Inc
1160 rue Levis, Suite 100
Terrebonne (Quebec) J6W 5S6

Tel.: 450-471-0796
Toll free: 888-332-3749
Fax: 450-471-5443 . 888-243-4562

info@electricenergyonline.com
www.electricenergyonline.com

  Press

  Jobs

  Events

  Subscription

  News

  Magazine

  News on your smartphone

© 2014, Jaguar Media inc. All rights reserved. 1996-2014